Behind the brick, 141 timber modules


The European Modular Briefing

Dear Reader,

Behind a brick facade in Vä, outside Kristianstad, stand 141 timber modules from two factories in Värmland.

Last Wednesday the Swedish Prison and Probation Service opened its new prison there, a little over a year after the first sod. The building went up fast. Everything around it, from the decision to the admin block, tells a slower story, and that is where this week's issue starts.

Around it sit a Commission web page that gives the same market two very different sizes, a Dutch factory that can make about 4,000 homes a year and is waiting for officials to trust a certificate, 65 timber modules craned into a concrete frame east of Paris, 18 homes for Wiltshire being finished in Vietnam, and a founder admitting that the ambitions were too big.

Every story links to its source and ends with my take, clearly marked.

Lars

In this issue
1. Sweden, 141 timber modules behind brick
2. Brussels, one market and two sizes
3. Netherlands, type approval for a house
4. France, 65 timber boxes in a concrete frame
5. England, eighteen homes and five weeks at sea
6. Austria, the ambitions were too big
7. Funding and programmes
8. Market and competitor moves
9. New technologies and innovations in modular
10. Numbers of the week
11. Calendar: next six weeks
12. Public tenders worth a look
 
Know someone who should read this? Forward to a friend. Got it from a friend? Subscribe here.
 
1. Sweden, 141 timber modules behind brick

On 18 November Kriminalvården, the Swedish Prison and Probation Service, inaugurated its new prison at Vä outside Kristianstad, a little over a year after the first sod. Moelven puts it at about 200 places, security class 2, certified BREEAM Excellent, with solar panels on the roof of the housing block.

The housing block is built from 141 prefabricated timber modules made at Moelven Byggmodul's factories in Säffle and Torsby, clad in brick. NCC and Intea are named as partners. Moelven also supplied a temporary administration building with intake and office space, made of 56 site-hut modules from its factory in Kil. The first inmates arrive in early 2027, and about 200 staff have already been recruited.

At the opening, Kriminalvården's Stefan Karström said Kristianstad had waited about 20 years for a new prison. "Better late than never," he said, as quoted by Moelven in Swedish.

My take

Twenty years to decide, one year to build. The modules were never the slow part.

The detail I keep coming back to is the admin building. The intake of a security class 2 prison sits in 56 site huts, the same family of boxes you find at the gate of every building site, and Moelven calls it temporary. I would like to see the date it actually leaves.

 
2. Brussels, one market and two sizes

The European Commission runs a page on offsite construction as one of its Competitiveness Coordination Tool projects, which Built Offsite picked up last week. It says a pilot was proposed in the Affordable Housing Package and the European Strategy for Housing Construction, and that a scoping dialogue with industry and Member States is planned for the fourth quarter of 2026. Demonstration projects "could be envisaged" as testbeds. No budget is named.

The page says offsite construction shortens construction times by 20 to 60 percent and cuts waste by 10 to 15 percent. In the main text it puts the growth potential of "this growing market" by 2040 at up to 1 trillion euros, a 600 percent increase in revenues. In the box of key figures below, the overall value of the EU market by 2040 is 68.8 billion euros. Both numbers are on the same page, and neither comes with a source.

My take

A trillion and 68.8 billion can both be right if one is the world and the other is Europe. The page does not say so, and somebody will copy the bigger one into a slide by Christmas.

The number I would actually like to see is the one the pilot promises to look for, the legal bottlenecks. A module that is approved in one country and needs a fresh fire test at the next border costs more than any market forecast can earn back. Nobody has put that figure on a web page yet.

 
3. Netherlands, type approval for a house

On 20 November Binnenlands Bestuur, the Dutch magazine for public administration, walked through Van Wijnen's housing factory in Heerenveen. Robots set reusable steel formwork for concrete walls, fixed to the table by magnets to a tolerance of 1 millimetre, according to director Menso Oosting. He claims that about 60 people on one shift do as much work as 1,350 construction workers in a traditional process.

The magazine says the factory can build about 4,000 homes a year but does at most a third, because demand for factory homes is smaller than supply. The national government's ambition, as reported there, is that within four years half of all new homes start life in a factory.

The fix being pushed is type approval. Cars are not inspected one by one before they go on the road, and inspectors and municipal supervisors would likewise rely on a certificate that the testing body Kiwa issues for a factory type. Van Wijnen has one, the magazine says, and Plegt-Vos and BAM expect theirs. In the Arnhem and Nijmegen region, Jack van Hoof, hired by the Gelderland authorities to push industrial building, now runs sessions with the fire service and the environment agency to show how the certification works.

My take

The headline says the bricklaying robots are hidden. The bottleneck is not hidden at all. It sits at a desk in the town hall and would like to see the drawings again.

Type approval is the right idea, and the car comparison is honest about the catch. A car is approved once and then drives on any road. A house is approved once and then lands on different soil, a different sewer and a different fire brigade every single time.

 
4. France, 65 timber boxes in a concrete frame

In the Ancre de Lune eco-district in Trilport, Seine-et-Marne, the social landlord 3F is building 132 homes partly in a factory, the local paper La Marne reported on 14 November. There are 46 social rental homes for families and 86 homes for young workers, apprentices and students.

The young workers' residence uses 65 three-dimensional timber-frame modules made by Vestack at its factory in Saint-Germain-Laval, about 90 km away. Insulation, windows and checks are done there before transport. On site, Demathieu Bard ties the modules into the concrete structure and does the connections, finishes and fit-out. The family homes get timber-frame facades and prefabricated balconies. The paper counts five prefabricated products on the one job, timber modules, timber facades, concrete twin walls, and concrete balconies and stairs.

According to the developer, crews can set up to 20 modules a day. Work started in April 2026 and completion is planned for the second half of 2027.

My take

This is what most off-site building looks like in real life. A concrete frame, timber boxes slotted in, prefab balconies and stairs, and one general contractor making it all meet.

Twenty modules a day is the easy number to quote. The work that decides the job happens where a timber box meets a concrete wall, and two trades with two different tolerance tables have to agree who moves.

 
5. England, eighteen homes and five weeks at sea

NuHome, a main contractor based in London, says the modules for 18 homes in Wiltshire are in final works at the TLC Modular factory in Vietnam. Second-fix services, underfloor heating, decoration, cladding and windows are going in now. The scheme is four one-bed flats, four two-bed houses and ten three-bed houses for a registered provider, made from 32 modules in one production run.

Building Control issued Full Plans Approval on 13 October, after all 22 plan check items were closed, and approved the insulated raft foundations on all 18 plots in September. The modules are to ship together, about five weeks at sea to a UK port, and completion is due in May 2027. NuHome holds BOPAS Full Accreditation for the steel-framed system, with a 60-year assessed durability, according to its website.

For its two-bed house type, NuHome says five of the six modules ship as standard 20 ft containers and the one wide module goes on a flat rack.

My take

Factory homes for Wiltshire made in Vietnam will annoy some people. The order of work is the part worth copying. Foundations signed off before anything leaves the factory, plans closed item by item, one shipment.

Five weeks at sea is the easy bit. Anyone who has landed boxes on a site knows the hard week is the one when a crane, a raft poured months earlier and 32 modules built to somebody else's tolerances finally meet.

 
6. Austria, the ambitions were too big

Two weeks after several GROPYUS subsidiaries went into insolvency proceedings, chief executive Philipp Erler gave a press briefing. Der Standard reported on 19 November that he said the company had grown too fast and taken on too many projects at once, and that "the ambitions were too big". The trigger, the paper writes, was 73.1 million euros pledged by an investor in a financing round that never arrived.

The Austrian engineering company in Steinhaus near Wels, which built the machines for the Richen plant, is being wound up, and about 20 people lose their jobs. GROPYUS has also registered all 47 staff at its Vienna head office with the AMS early-warning system, which Erler said does not mean the head office will close. Production in Baden-Württemberg and the running sites, including a Buwog project in Salzburg, are to continue.

Erler put the capital need at about 50 million euros for the next 18 months. He wants to lose much less money next year and move towards break-even in 2028. Vonovia, which holds 25.05 percent through its Austrian subsidiary Buwog, has written off its stake in full, according to the paper.

My take

It is rare to hear a founder say it this plainly, and it deserves some credit. It also tells you where the money went. The robots were not the expensive part. Too many first projects at once were, each one a prototype with a client waiting.

Closing the shop that builds the machines is the most honest line in the whole story. You only keep a machine builder if you plan to build another factory soon.

 
7. Funding and programmes

Spain. On 17 November the Council of Ministers authorised the call for competitive grants to industrialised housing, up to 45 million euros. Europa Press reports 42 million euros in 2026 for the line on automation, robotics, digital tools and logistics in small firms, 3 million euros for technical evaluation and certification, and applications from January 2027.

Germany. The new federal housing company is to start in early 2027 as a GmbH with about 30 staff, n-tv reported on 16 November, citing finance ministry circles. The 2027 money stays blocked until the government gives the Bundestag budget committee a structured detailed concept, and only then are the first 20 million euros released. Total financing is put at 18 billion euros, 1.8 billion of it equity and 16.2 billion in loans the federal government will guarantee. The company will not build itself. It will award construction contracts and keep the homes, aiming for lower costs through serial and modular building. No number of homes and no rent cap have been given.

 
8. Market and competitor moves

Spain. Cecotec and the town of Almussafes signed the definitive agreement on 18 November for the industrialised-housing plant first set out in a protocol in October. The company's figures are about 150 million euros of investment, capacity for up to 6,000 homes a year and about 4,000 direct and indirect jobs, with Casas inHAUS as technology partner. The town is still meeting landowners to acquire the site of more than 515,000 square metres.

Netherlands. Woonstad Rotterdam and Daiwa House Modular Europe signed the realisation agreement on 11 November for 376 student studios and 5 wheelchair-accessible homes at Toepad, near the Woudestein campus. The homes are to stay on the site for 30 years. On the same page the company says its modular homes last 80 to 100 years.

 
9. New technologies and innovations in modular

Spain. Tecnalia coordinates SITEBOT, an EIC Pathfinder project under Horizon Europe in which teams of ground and aerial robots are to move and assemble industrialised building elements under human supervision, using lightweight modular components and reversible joints designed for robots. The partners over four years are Rovimática, OTH Regensburg and the École Nationale des Ponts et Chaussées. The project fact sheet names two climbing robots, a drone and a mobile base, tested on a lab demonstrator of about 5 by 5 by 2.5 metres. It is one of eight projects in the EIC's 2025 challenge on robot collectives for construction sites.

Portugal. The timber company Portilame in Viana do Castelo is developing the VEIA Modular System, a wood-frame system for walls, floors, roofs, facades and three-dimensional units, for buildings of up to four storeys. It is part of the R2U Technologies Modular Systems Agenda, funded through Portugal's Recovery and Resilience Plan. The company says its lab tests cover mechanical behaviour, acoustic insulation, air permeability and water tightness.

 
10. Numbers of the week

460. Relocatable homes that Portaal and Woonin have started building by Lunetten station in Utrecht, between two railway lines and the A27. They are to stand there for ten years and can then be moved and reused elsewhere. Handover is expected at the end of 2027.

170. Rental flats in eleven four-storey houses that the federal property agency BImA is building in Berlin-Düppel from room modules prefabricated in Coswig, Saxony, according to Entwicklungsstadt. The first phase is due in spring 2027.

 
11. Calendar: next six weeks

25 and 26 November 2026. London Build at Excel London, with a Modern Methods of Construction stage on both days.

15 December 2026, 10:00 to 12:30 CET. An online webinar of the EU High Level Construction Forum, one year after the European Strategy for Housing Construction, with particular attention to building permits and offsite construction, as announced by FIEC.

 
12. Public tenders worth a look

The Poitiers notice listed in issue 4 has been re-published by the Région Nouvelle-Aquitaine with a new deadline of 10 December, listed below.

Open public notices for modular, container and related industrialised building work. Deadlines below are 25 November 2026 or later. Each line links the official notice. Values appear only where the notice states them.

If you have ever worked in a site hut that was meant to go after six months, reply and tell me how many years it stayed.

Thanks for reading. If this was useful, please forward it to anyone who builds, buys or approves modular housing. You can also connect with me through the links below, and if you have a question, just hit reply. I read every message.

Best regards,
Lars

Podcast LinkedIn Instagram TikTok YouTube X WhatsApp
Forward to a friend    Subscribe here

The European Modular Briefing

Modular, container and off-site housing in Europe, and everything beyond. Every Monday at 8am, by Lars Janowski.

Read more from The European Modular Briefing

The European Modular Briefing Dear Reader, The Richen plant was built for three shifts. It has been running one. That is this week's picture of modular building in Europe. A timber-hybrid housing factory with about 50 robots and a bill of about 75 million euros, and a contracted investor payment that, the company says, never arrived. On 5 November a Berlin court put the German subsidiaries under a provisional administrator. Work continues. The parent company in Vienna says it is not in the...

The European Modular Briefing Dear Reader, In Oss they put out a small tribune so neighbours could watch houses arrive by crane. That is this week's picture of modular building in Europe. Not a factory tour. A row of seats facing a plot, while 39 finished apartments swing in from a truck. Beside it sit a five-storey timber stack that does not look modular, a priced garden home for Irish back gardens, a design contest for nineteen flats on Gran Canaria, a Valencian protocol for a plant that...

The European Modular Briefing Dear Reader, Modular building has a speed problem, and it isn't in the factory. This week the fastest numbers in Europe were crane days. Ten days for 48 modules in Barcelona. One day for a concrete house in the Ain. The slow numbers sat around them, in permit files, zoning plans, appeal courts and legal status that runs out before the building does. So this issue is about the clock, and where the time goes once the box is already finished. Every story links to...